Beginning Construction |
 |
Foundation completed and Mike putting down the
girders after doing the risers and mud sill. It is 36 feet long, and 17
feet wide. Those dementions were used because that is how long the concrete was in
the back, and how far it was to the edge of the house. Seemed logical at the time... |
 |
Putting in the Floor Joists. Had
some challenges with the City's building inspectors, but they showed me the error of my
ways, and made me correct everything. ha... |
 |
Floor Joists completed, rough Plumbing in, and floor
insulation completed. |
 |
Floor glued and nailed into place. Plumbing
easier to see. Plywood is 1 1/8" T & G.
Have picture of Gloria doing a little dance on the smooth plywood floor. |
 |
Two outside walls up. Had to get 6 neighbors to
help me lift them into place. Have removed the old stucco and
part of the roof off the old section of the house. That window will eventually
become a closet doorway. |
 |
All the walls are up and plumbed. Mike is
nailing the exterior sheathing. |
 |
Exterior sheathing is up, and now putting up the
trusses. This is where Mike smashed his thumb. He eventually lost
that nail. |
 |
The roof sheathed. This is
where one of the pieced of wood slid off the roof and landed on Mike's toes. He had
black toes for a few weeks. He eventually lost a toe nail. |
 |
- Click on house plan on left or button
below to see the
|
 |
- Click on the photo on the left
to see the
|